You have set up a Flow to automatically assign a resource's manager to the approver field on
Timecards. Users have reported that submitted Timecards are going to the Project Manager for
approval and not the resource's manager. Of the following, which could be a reason for this?
Question No 2
Your company has both full time and part time resources. From a Human Resources perspective, part
time resources can work any number of hours per week. From a Resource Planning perspective,
management has agreed that part time workers can be estimated at 20 hours per week.
Based on this information, how many work calendars should be created?
Question No 3
Project Managers would like to display several fields prominently on the Project Lightning Page.
Which PSA Lightning Component could you use to meet this need?
Question No 4
You are notified that some approved Miscellaneous Adjustments records are not getting picked up in
the Billing Event Generation process during month end billing.
Which two of the following system settings do you need to have in place for Miscellaneous
Adjustments to get picked up in the billing run? (Choose two.)
Question No 5
Which of the following custom settings can be specific to a User?