Which of the following scheduling techniques identifies the successor activities and the
predecessoractivities to assist the project manager in sequencing the project work?
Question No 2
You are the project manager of the NHGQ project for your company. You must create and distribute
performance reports every week to your key project stakeholders. What communication technique
do you normally use to distribute reports?
Question No 3
Your project team is executing the project plan and things are going well. Your team has reached its
first milestone and is now in the second phase of the project. The project stakeholders have
requested that you find a method to reduce the duration of the project. They will reward you and
your project team with a 25 percent bonus of the project costs if you can finish the project thirty days
earlier than what was already planned. The stakeholders, however, will not approve any additional
labor costs as part of the agreement. Which approach could you use to shorten the duration of the
project?
Question No 4
The Define Activities process is the first process in the project time management knowledge are
a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave
planning, templates, and expert judgment. Which one of the following is not an output of the Define
Activities process?
Question No 5
Examine the figure given below:
If Activity B takes eight days to complete instead of five days as schedule, how long can you now
delay Activity H?