Practice US Green Building Council LEED-AP-BD-C Exam Questions
Page: 1/61 Total 305 Questions
Question No 1
Which of the following buildings meets the Minimum Program Requirements for LEED certification?
Question No 2
Which of the following would be most useful to a school project that is attempting to pursue Water
Efficiency Credit, Indoor Water Use Reduction?
Question No 3
A project has total waste of 20 tons (18.1 tonnes) that includes the following
• 8 tons (7.3 tonnes) of recycled demolition steel and concrete
• 2 tons (1.8 tonnes) of trees cleared from the site
. 3 tons (2.7 tonnes) of commingled scrap with 40% diverted
. 6 tons (5.4 tonnes) of used furniture donated to a non - profit organization
• 1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the manufacturer
What is the percentage of diverted waste for Materials and Resources Credit, Construction and
Demolition Waste
Management?
Question No 4
A LEED Building Design and Construction project includes an outdoor stage for theatrical
performances. In pursuit of Sustainable Sites Credit, Light Pollution Reduction the engineer has
specified an LED fixture to illuminate actors on the stage while limiting light pollution. Which of the
following suggestions should the LEED AP give to the project owner?
Question No 5
During the early stages of a LEED for Schools project, the team was able to reduce the number of
lighting fixtures in classrooms by 25% because the project team selected paint color whose light
reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of
applying which of the following credits to the project?