Management has requested a 15 - minute battery bank assuming full load on the UPS. The UPS
vendor has provided the following specifications of the UPS
• Rated power 30 kVA
• Rectifier input voltage 400 V/3 phase
• Rectifier input power factor 0.8
• Battery rated voltage 384 V
• Number of cells 192
• End of discharge voltage 308 V
• Inverter output voltage 400 V/3 phase
• Inverter output power factor 0.8
What information is missing to perform the battery calculation?
Question No 2
The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner
inside the computer room.
Is this a good practice from an early smoke detection point of view?
Question No 3
You need to determine the strategy for the cooling audit. All the servers are based on a front - to - rear
(F - R) airflow design.
Which location for the temperature/humidity measurement should you recommend for the audit?
Question No 4
You are installing new copper cabling.
What is the advantage or disadvantage of choosing pre - terminated category 6 or 6A cabling?
Question No 5
When are the wet bulb and dry bulb temperatures identical?